Construction Segment C

Upcoming Activities
 

From Nob Hill Road to Pine Island Road

  • Continue drainage installation along eastbound S.R. 84
  • Crews will continue to place “bulkhead”, or retaining wall, along the North New River Canal, parallel to westbound S.R. 84
  • Concrete barrier wall will be placed along the center median of I-595

Pine Island Road Intersection

  • Continue installing foundation for the I-595 overpass bridge at Pine Island Road
  • Concrete barrier wall will be placed along the center median of I-595

From Pine Island Road to University Drive

  • Crews will place material to raise median to the same height as the roadway
  • Placing temporary pavement on westbound S.R. 84 to widen the roadway
  • Concrete barrier wall will be placed along the center median of I-595

From University Drive to Davie Road

  • Concrete barrier wall will be placed along the center median of I-595
  • Clearing along the North New River Canal will continue