From Nob Hill Road to Pine Island Road
- Placing temporary pavement on westbound S.R. 84 to widen the roadway for a traffic shift
- Drainage installation along eastbound S.R. 84
- Crews will continue to place “bulkhead”, or retaining wall, along the North New River Canal, parallel to westbound S.R. 84
- Concrete barrier wall will be placed along the center median of I-595
Pine Island Road Intersection
- Continue installing the foundation for the I-595 overpass bridge at Pine Island Road
- The U-turns for both directions of S.R. 84 at Pine Island Road are closed through October 2010
- Concrete barrier wall is placed along the center median of I-595
|
From Pine Island Road to University Drive
- Temporary drainage installation
- Crews will place material to raise the median to the same height as the roadway
- Placing temporary pavement on westbound S.R. 84 to widen the roadway
- Concrete barrier wall is placed along the center median of I-595
- Microtunneling at the AMF Davie Lanes continues
From University Drive to Davie Road
- Place temporary pavement on westbound S.R. 84 to widen the roadway for a traffic shift
- Placing sod along the shoulders of the temporary pavement
- Clearing foliage along westbound S.R. 84
- Concrete barrier wall will be placed along the center median of I-595
|