Construction Segment C

Current Construction Activities
 

From Nob Hill Road to Pine Island Road

  • Placing temporary pavement on westbound S.R. 84 to widen the roadway for a traffic shift
  • Drainage installation along eastbound S.R. 84
  • Crews will continue to place “bulkhead”, or retaining wall, along the North New River Canal, parallel to westbound S.R. 84
  • Concrete barrier wall will be placed along the center median of I-595

Pine Island Road Intersection

  • Continue installing the foundation for the I-595 overpass bridge at Pine Island Road
    • The U-turns for both directions of S.R. 84 at Pine Island Road are closed through October 2010
  • Concrete barrier wall is placed along the center median of I-595

From Pine Island Road to University Drive

  • Temporary drainage installation
  • Crews will place material to raise the median to the same height as the roadway
  • Placing temporary pavement on westbound S.R. 84 to widen the roadway
  • Concrete barrier wall is placed along the center median of I-595
  • Microtunneling at the AMF Davie Lanes continues

From University Drive to Davie Road

  • Place temporary pavement on westbound S.R. 84 to widen the roadway for a traffic shift
  • Placing sod along the shoulders of the temporary pavement
  • Clearing foliage along westbound S.R. 84
  • Concrete barrier wall will be placed along the center median of I-595