Construction Segment C: Construction Photos

Click on an image below to view an enlarged version
April 2010
Augering for soil anchors at the receiving pit. Work platform in place at the receiving pit area adjacent to the NNRC.
 
Bergeron constructing working platform on the south bank of the NNRC. Barrier and barricades placed for WB SR 84 lane reduction.
 
Shoreling Foundation setting up template for test pile at Pier 2. Shoreline Foundation pile driving equipment at Flamingo Road.
 
Driven sheet piles for microtunneling pit within bowling alley parking lot. Johnson Davis installing drainage on NW quadrant of Pine Island Road and SR84.
 
Signal Group working on signalization on Pine Island Road and SR 84 WB. Johnson Davis installing drainage along SR 84 WB.
 
Test pile shown on Pier 3, Pile No. 12. Three beams and two plates attaching the end barrier wall to bridge wall.
 
Asphalt placement on EB I-595. EB I-595 approaching Pine Island Road: barrier wall attachment.
 
EB SR 84 drop off corrected. WB I-595 barrier placement operation.